November 27th marked the beginning of Phase 2 for the Killam Library Deep Energy Retrofit. The company doing construction, MCW, is now working on the second floor of the library.
- Closures: The book stacks, the map room and area with compact shelving, and room 2902 will remain closed until the end of January.
- Borrow requests: Please use Novanet Express or speak with staff at the Killam Library Service Point (KLSP) for requests from areas that are closed.
Music Room Reopening
- The Music Collection room will reopen on Friday, December 1.
Noise and Construction Outside
- Outside the Student Accessibility Centre, MCW will be replacing a concrete slab. Jack hammering, vibrations, and noise are expected between December 20 and January 6, 2024.
Main Stairwell Closure (Phase 2.2)
- To reduce disruption, the Killam’s main stairwell will close over the Christmas holidays. The closure is scheduled from December 23 to January 8, 2024. More information on the logistics of this will be coming soon.